The Deep Tunnel Sewerage System (DTSS) is a massive integrated project being developed by the Public Utilities Board (PUB) in Singapore to meet the island country’s long term clean water needs through the collection, treatment, reclamation and disposal of used water from industries, homes and businesses. The DTSS project involves construction of two large deep gravity tunnels, 6.5 m in diameter and 80 km long in total, located about 50 m below the surface, to carry sewage to three centralised water reclamation plants (WRP). The used water is treated and purified to a high quality water known as NEWater. The excess treated effluent is discharged through deep sea outfall pipes into the straits of Singapore.

DTSS阶段II通过30公里长的南隧道,70公里的连杆下水道,TUAS WRP和12公里的深海排排威将隧道系统延伸到新加坡以西。

我们的营销助理在该地区的仪器阶段2项目链接下水道的仪表和监测工程以及Tuas水填海工厂的工程。该项目中近215个电压力计和50个弧形可焊接应变计量在项目中。所有传感器(100%)均令人满意地运营到今天。